Project #10 Resurface Streets in the Town of Ridgeville
Resurfacing the streets in the Town of Ridgeville. Removal of existing asphalt sidewalks and construction of concrete sidewalks to
A.D.A. Standards.
Total length of sidewalks: 1.63 miles. Total length of resurfacing: 2.79 miles.
PROJECT COMPLETED
ROAD | NAME | MILES |
S-18-279 | ACADEMY | 0.16 |
S-18-282 | BEACH | 0.55 |
S-18-347 | CRAB APPLE | 0.07 |
S-18-348 | DORCHESTER | 0.13 |
S-18-740 | HORSESHOE | 0.2 |
S-18-5 | MAIN | 0.41 |
S-18-174 | MILL | 0.18 |
S-18-741 | MURRAY | 0.21 |
S-18-77 | N. RAILROAD | 0.29 |
S-18-202 | NEW | 0.06 |
S-18-203 | OAK | 0.06 |
S-18-78 | S. MAIN | 0.47 |
Click to view to Project Status